Tatopani Mini hydroelectric Project

Executive summary

The Tatopani Mini-hydro Project is located on the left bank of Marsyangdi River along the popular trekking route to Manang. The project lies within the Ghermu Village Development Committee of Lamjung District, Western Development Region, Nepal.
The Tatopani Mini-hydro Project is a run-of-the-river type scheme, Tatopani Khola being its source. The installed capacity of the plant is 210 kW. The headworks consist of a gabion weir with RCC wall sandwiched between the gabion boxes, which diverts the flow of 200 l/s through the intake to the intake canal. Grits and coarse sediments get deposited and flushed out from the gravel trap located just after the intake. The excess flow is spilled through the spillway incorporated in the intake canal and the rest of the flow enters the settling basin. The settling basin is of 2.5 m wide and 18 m long. The settling basin also acts as a forebay since the penstock pipe starts right from the settling basin end. The settling basin is designed to trap particles upto 0.2mm size with a settling efficiency of 90%. The sediments get deposited and flushed out from the settling basin and the sediment-free water then enters the penstock pipe. A suitable submergence depth is provided for the penstock pipe. A spillway and a flushing canal are provided to discharge the excess flow and the sediments to a nearby stream through a spill canal. 300 mm internal diameter, mild steel penstock pipe conveys the design discharge of 200 l/s to the turbine. The 600m long penstock pipe is supported all along the length by support piers at a regular interval of 5 m and anchor blocks at the bends. To economize the volume of mild steel, the thickness of the penstock is varied from 5mm to 7mm along the length of the penstock pipe. Turbine could be a single unit of turgo or a pelton. The turbine is directly coupled to a generator, which then generates the electricity. The generated electricity will then be transmitted through an 11kV line to the national grid.


The gross and the net head of the scheme are 151 m and 132 m respectively. The design flow of the scheme is 200 l /s.
The project is expected to be commissioned after about 8 months from the start of the construction work and the estimated total cost of the project is about 21.6 Million Rupees.


This study has shown that the scheme is technically viable and economically attractive with the current energy buying rates of Nepal Electricity Authority (NEA).

Project salient features

Location Lilibhir, Ghermu VDC, Lamjung
Name of the River Tatopani
Installed Capacity 210 KW
Gross head 151m
Net head at runner 132m
Inflow design flow 200 1/s
Catchment area 5.75 km2
Penstock type/ length / size / thickness Mild Steel / 600m / 300mm / 5mm-7mm
Settling basin/Forebay 18m long, 2.5m wide
Turbine type Turgo/Pelton with deflector system
Dam type Gabion Weir with RCC cutoff wall
Powerhouse plinth area 66.5 m2
Transmission line length 0.3km
Transmission voltage 11 KV
Total project cost NRs 21.6Million

1 Introduction
Lamjung Electricity Development Company (LEDCO) on behalf of Syange Bidyut Company undertook a detail feasibility level study of the Tatopani Mini-hydro Project (TMHP). The purpose of the study is to provide an updated financial and technical assessment of this project using a grid connection and selling power to the Nepal Electrical Authority (NEA). The TMHP is being developed by Syange Bidyut Company as a locally owned grid connected mini-hydro. The owners of the present 183 kW Syange Mini-hydro Project along with other members of the community have committed to invest in developing the scheme. LEDCO will provide the engineering and technical support that is necessary to develop the scheme.

The experience gained from developing Syange Mini-hydro Project of similar size will be an added advantage to develop this project.

The study has shown that the installed capacity of the plant will be 210 kW with a design discharge of 200 l/s. The minimum power will be less than this during the dry period. The electricity generated will be connected to the 11kV line, which has already been constructed from Bahundanda to Syange.

1.1 Location
The village of Lilibhir is in the Ghermu VDC of Lamjung district. It is located on the tourist trekking route along the Annapurna Circuit. Lilibhir is a small village located at latitude of 280-20'' and longitude of 840-25'. The project area lies to the left bank of Marsyangdi River.
The project area is shown in Appendix A.

1.2 Access
The nearest road-head (black topped) to the project site is at Besisahar, the headquarter of Lamjung District. A seasonal road suitable for motor vehicles is extended to Bhulbhule. Lilibhir is 5-hour walk from there. Mules take one day to reach Lilibhir from Bhulbhule and it is cheaper than using porters for bulk supply of goods.

2 Background
2.1 Pre-feasibility
The developers of the Syange Mini-hydro Project showed interest in implementing another grid-connected mini-hydro project of similar size in this region as such projects proved very attractive economically. Moreover, the projects of this size required capital cost that could be raised by the shareholders themselves and could be constructed within a year. LEDCO performed the pre-feasibility study of Tatopani Khola. The results of this report were the following:
The scheme is a run of the river type with an installed capacity of 210 kW.

The scheme consists of a semi-permanent diversion structure with an intake at the left bank of Tatopani Khola. The water from Tatopani Khola is conveyed to the settling basin cum forebay through a masonry intake canal. Mild steel penstock pipe conveys the design discharge to the turbine, which is coupled to a generator. The electricity generated will be transmitted to the 11kV national grid to be sold to NEA.

2.2 Market Summary
Although Nepal is characterized as a hydro rich country, only a small portion of its total hydro capacity has been harnessed to produce hydroelectricity. At present the Integrated Nepal Power System (INPS) has a total installed capacity of about 610 MW of which about 545 MW is generated from hydro resources. Of the hydropower plants only 92 MW (cascaded between Kulekhani I of 60 MW and Kulekhani II of 32 MW) is from storage plants and the rest is from run-of the river schemes. The annual energy generation is about 2380 GWh. The entire system has about One million consumers.
The Nepal Electricity Authority (NEA) resorted to load shedding to manage the supply of power by cutting off supply at different load centers of the country on a rotational basis, until very recently.
There are several power plants that are under construction, which will significantly contribute to the grid capacity. The forecast carried out by NEA, however, predicts that even with the augmentation of power supply from the power plants under construction, there will be a shortage of power supply after a few years. The NEA, in 1998 announced a policy to support the private sector of small hydropower developers. With this policy it is envisaged that numerous small-scale hydropower projects will be developed in the near future.

For more information, please contact our ledco office in Kathmandu.
Last modified: 8 May, 2005 . Contact webmaster for website problems.
All material is copyright © Lamjung Electricity Development Company.